Name of Project:
Deerfield Facility, Lighting Improvements
Newark, Delaware
Owner
MBNA America Bank, N.A.
Wilmington, Delaware
Project Team
Charles Doble, Creedon Controls Electrical
Peggy Hill, United Electric Supply
Challenge
Replace approximately 1600 fluorescent fixtures with new fixtures and install 80 Lutron® daylight harvesting dimming control zones without affecting operations at a 24/7, 2 million square foot facility.
Solution
Installed fixtures and wiring at night on third shift when operations were at their slowest. Provide temperature lights and replaced fixtures in zones so that operating could continue. Completed on time and within budget, December 2001. Value: $235,000
Name of Project:
Deerfield Site, Mechanical Improvements
Newark, Delaware
Owner
MBNA America Bank, N.A.
Wilmington, Delaware
Project Team
Charles Doble, Creedon Controls Electrical
Pat Morley, Delcard Associates
Craig Kurtzhals, Paragon Engineering
Challenge
Replace 2 boilers, 4 cooling tower, 5 large circulating pumps and associated systems without affecting 2 million square foot facility operating 24/7.
Solution
Coordinated with mechanical contractor to insure electrical work was completed before each system was changed out. Completed March 2003. Value: $425,000.00
Name of Project
Deerfield Wings 1, 2, 3 and 4, Electrical Upgrades
Newark, Delaware
Owner
MBNA America Bank, N.A.
Wilmington, Delaware
Project Team
Charles Doble, Creedon Controls Electrical
Craig Kurtzhals, Paragon Engineering
Jeff Vaughan, Diamond Group
Challenge
Install a 1200 KW self-contained generator
set and upgrade feeders to ten substations
without affecting production at a two million square foot office building. Finish the project on a fast track schedule to meet the owners' Y2K needs.
Solution
Coordinated phased shutdown of the substations with careful planning in order to complete each changeover within a limited time window. Increased and reduced manpower to meet schedule requirements. Project completed on time December 2001.
Value: $610,000.
Name of Project
Deerfield Site Wings 3 and 4, Electrical Modifications
Newark, Delaware
Owner
MBNA America Bank, N.A.
Wilmington, Delaware
Project Team
Charles Doble, Creedon Controls Electrical Jeff Jordan, Enerwise Global Technologies
Challenge
Install a new 2000 KW generator, 5KV substation, 1600 Amp, ATS switch, eight switchboards and replace 70 lighting and power panels including feeder in a 2mm square foot office building which operates 24/7.
Solution
Installed all new work employing two shifts to minimize disruption and coordinated shutdowns with owners' work schedule. Project completed 2 month's early, February 2002. Value: $750,000.00
Creedon Controls Electrical Contractors
3424 Old Capitol Trail, Wilmington, DE 19808